Logo Loading
SITE INSPECTIONS

02 JULY 2022 – SITE VISIT

Milestones Dashboard Block wise Estimated completion dates Estimated Amenities completion dates Disclaimer: Above dates have been derived based on site inspection findings and revised project plan submitted by VGN project team. The dates are subject to change due to external factors such as cash flow, materials availability, Labour availability, Covid risk etc. which are not [...]
Read more
SITE INSPECTIONS

25 JUNE 2022 – SITE VISIT

Attendance: Fairmont Flat Owners Association representation: Mr.Rathinavel (B1-5B), Mr.Asokan (B6-9A), Mr.Dayanand (B1-6E) Mr.Nagarajan (B5-10E) + few more customers joined late.VGN Representation: Mr.Vidyasagar, Mr.Mahindran + few more site engineers. Milestones Dashboard BLOCK-B & BLOCK-D MILESTONES AND ESTIMATED COMPLETION DATES COMMON AMENITIES ESTIMATED COMPLETION DATES Disclaimer: Above dates have been derived based on site inspection findings and [...]
Read more
SITE INSPECTIONS

18 JUNE 2022 – SITE VISIT

Attendance: VGN Project Team - Mr. Mahindiran (GM), MR. Vidyasagar (Project Manager), Mr. Venkat (Site Engineer) & members from the project team. No representation from CRM team. Site Inspection Team - Mr. Rathinavel (B1-5E), Representative of Mrs. Ramapriya (B5-6E), Mr & Mrs. Vijay (B5-12D), Mr. Vijayaraghavan (B3-9C) & Mr.Ganesh (B5-2D) + Few more customers joined [...]
Read more
SITE INSPECTIONS

11 JUNE 2022 – SITE VISIT

Milestones Dashboard Milestones & Dates for Block-B and Block-D Milestones & Dates for Common Amenities Disclaimer: Above dates are a mere estimates based on site inspection and dates provided by the site team. These dates are likely to gain or lose timeline based on practical progress. Observations by the site inspection team: Block B1 - [...]
Read more
HOUSE WARMING CEREMONY

B1-8E House Warming Ceremony

Glimses of house warming ceremony of B1-8E by Mr. KarthiK and Mrs. Thapasvi on 9th of June 2022. The steering committee and all members of the association wishes the family for everlasting joy and happiness in your new house. Note: Leave your wishes to the family in the comments box below.
Read more

4 JUNE 2022 – SITE VISIT

Below site inspection report for the inspection carried out on 4th June 2022 (Saturday): Above Block-wise construction progress and revised dates Above report - Common Amenities and revised dates Findings by the inspection team: B6 Block lift work has been delayed by 10 more days.Additional manpower needed for shuttering work. Only 12 workers available in [...]
Read more
SITE INSPECTIONS

7 MAY 2022 – SITE VISIT

Site inspection report below based on data collected from VGN team: Block wise Progress Report: Common Amenities Report: Take a look at the pictures taken during the inspection below: Take a look at the illustration video below by the site engineer on how the sliding windows drain the water and prevent water entering inside during [...]
Read more

Compare